We're right back on track say tram chiefs

TRAM chiefs today insisted the first phase of the £545 million project was on track for summer completion, despite new figures showing one section of the work is only a third finished.

Utility diversion works, which should have been completed months ago, are still only 70 per cent complete, with work between Newhaven and Leith Walk only 39 per cent done.

Shirley Anne-Somerville, the Lothians MSP who obtained the latest figures using freedom of information laws, said the works slippage showed the tram project had now gone from "fiasco to farce".